Dirt Alert: WAC window replacement among projects underway across campus

July 31, 2011 at 10:09 pm

Roof work, window replacement, painting and office construction—all are underway across campus this week. Below, a breakout of what’s happening and where.

Chapin – Belwah is getting a facelift this month, with wood replacement, fascia and gutter restoration, and painting underway. The steps and a few yards of sidewalk in front of Chapin will also be removed and replaced in the coming weeks, with a slight realignment to the patio and sidewalks also planned.

The walkway between 840 and TKE is being widened and trip hazards removed this week as well.

WAC – The World Affairs Center is also getting some attention right now. Window replacement began last week and will continue in the days ahead.

Smith – Roof work on Smith is expected to be wrapping up at the end of next week.

Library – The library roof replacement is expected to finish up shortly after the Smith work (physical plant expects work to be complete in three weeks).  

Sports Center – The office spaces under construction in the sports center should be finished before the class of 2015 arrives on Monday, Aug. 22.

Strong Stadium – The turf surface should be installed shortly. In the meantime, wall patching is being completed and will be followed by a new coat of paint on the stadium this week.

Bushnell Street – The city reports that the curbing is being completed and road replacement will follow. The completion date is still August 12.