Project Timeline

April 2007 Groundbreaking
Site excavation begins
Foundations begin
July 2007 Foundations/basement complete
Structural steel begins
August 2007 Structural steel complete
Concrete floors complete
Exterior walls begin
September 2007 Mechanical/Electrical /Plumbing (MEP) begins
October 2007 Curtain wall /glazing begins
Partitions/studs begin
December 2007 Exterior walls complete
Curtain wall /glazing complete
January 2008 Drywall begins
HVAC installation begins
February 2008 MEP rough-in complete
Interior fixtures /finishing begins
March 2008 HVAC installation complete
April 2008 Drywall complete
Elevator installation
May 2008 Mayer Hall project begins
Packing for move
June 2008 Interior fixtures/finishing complete
Test and balance systems
July 2008 Punchlist complete
Move to Center for the Sciences
Chamberlin deconstruction begins
August 2008 Classes begin
September 2008 Mayer Hall project complete
October 2008 Chamberlin deconstruction complete
November 2008 Greenhouse begins
Site concrete work begins
February 2009 Greenhouse complete
Site foundations/bridges complete
April 2009 Garden decking complete
June 2009 Site landscaping complete

Beloit College | 700 College Street | Beloit, WI 53511
webmaster // Copyright © 2007

Academics Admissions Student Life
About Campus Resources Athletics
Beloit College
Directories
Site Index Search


Untitled Document Green Building
Building Facts
Architect's Renderings
Floor Plans
Project Timeline
FAQs
Departments and Programs
Impact on Students & Faculty


Untitled Document Science at Beloit
Science and Society
About Our Campaign

Ways to Give

Contact Us
Photo Gallery
Make an Online Gift